Worm farm waste system

We spent a fair bit of time researching septic systems; contemplated a composting toilet as an interim solution (but then realised that we would still need some kind of treatment system for our grey water) so decided on a worm farm waste system from A&A Worm Farm Waste Systems.  The service we received brilliant and I would not hesitate to recommend them.

The system includes a worm farm (essentially worms in a pit where all the solid components of waste go) and a series of overflow pipes downhill of the pit to filter the water waste.  The only limitation is that stock and food crops cannot be grown over the top of the pipes.  We bought a system that would cope with the shed toilet and the bathroom and ensuite planned for the house and a family of 6. 

This system worked in perfectly with our plan for a sustainable home.  There are no nasty chemicals, no need for pumping and dumping of solid waste and all the nutrients from our waste will fertilise the grove of Acacia melanoxylon trees that have since germinated near the site.
Delivery

My mad attempt at amusing the children while waiting for some action - pick up Little Miss and get Padawan to try to catch us
The kids tried to hide from the wind behind the tank and learned the hard way the laws of fluid motion

Swing time

Pure joy - Padawan gets to ride in the excavator
The pit is dug

The tank is installed

The vent pipe lasted a grand total of 3 days before the wind won and snapped it off at ground level.  The kids subsequently used it as a bridge on their 'fort'


Once the footings were complete we could measure up for the location of all the slab protrusions.  There were only two as we had worked hard to reduce them as much as possible.  Being amateurs, we were trying to make things as easy as possible for ourselves.  In doing so, we decided to have the kitchen and bathroom/laundry sink drain through the walls leaving only the toilet and shower running through the slab itself.

We struggled for weeks to find a plumber and eventually spoke with Mark from MBM Services in Moe who agreed to come out and provide us with a free quote.  Mark was really helpful and gave us loads of pointers.

We had Mark and his offsider come out to put the penetrations in.  They were a lot smarter more efficient and small digger for the job :
Mechanical shovel
 The large round penetration is the 'basin' catchment for the shower.  It's designed such that when you put the shower into place the drainage hole does not have to perfectly fit where the pipe it.  As each and every shower base is different, we actually purchased ours before we called our plumber in so we knew exactly where the final position of the shower is.

Toilet and shower penetrations
Pipe connecting to the worm farm




Dig, dig, dig

The site for the shed was levelled after the driveway was put in and looked like this:
View to the south east

View to the north east
The mound of dirt to the south of the cutting is the topsoil that has been set aside to use at a later stage.  The plan is to use that soil to create raised vegetable gardens to grow our own produce.

In an effort to save money, we decided to dig the footings by hand.  I do not recommend this.  To anyone.  Unless you have the contestants from "Biggest Loser" coming to do a challenge and dig the footings for you, perhaps.  The task of digging the footings by hand was made even more challenging by the fact that we were mostly digging into bedrock. 

We had a tricky time working out how to mark the site to cut the footings as we didn't have a laser sight.  So, we reverted to the old school technique of string lines.
Calculating is not my forte so I leave it to the mathematician

The string lines started out pink and by the time we finished digging they were bleached white by the sun and tied back together a million times after being pulled apart by Willie the wombat
 You can see in the photo above that we had to use spray paint in an attempt to make sure that the footings were straight as the wind at the block can be unrelenting and led to the string lines blowing about 50mm to the east of where they were meant to be.  We had to re-tighten the string lines each morning to get them to be where they were meant to be.  The only problem with the spray paint was that the dirt would fall away in clumps and the line would be lost.  In the end we ditched the spray paint and learned to get our eye in to account for the wind and ensure that the footings were correctly placed.

We raised the string lines off the ground to reduce the number of times the string was cut when the footings were being dug.  Luckily my husband is a deft hand at tying knots! Note: this became a repeating trend, where I would try to help and my poor husband would end up correcting my mistakes.

It might not look like much but setting up the strings took us about 2 weeks.  There was a surprising amount of maths involved in making sure the corners were at right angles and that the lines were oriented north-south and east-west.  The compass skills learned at uni came in surprisingly handy!

At the time, I was working from home on a full time basis so I would get up early in the morning and work from 0500 to about 0900 when the family had finished breakfast.  We'd then head to the block to work there and once the kids were in bed at night I would work again. 

The great dig begins

We learned pretty quickly how important it was to wear protective eye wear.  It is amazing how those small shards of rock flew through the air and would land with such precision in our eyes!

The kids spent a lot of time digging too

It was pretty tough going for our unconditioned office bodies (my hubby retired from work in 2006) so I managed to perfect my shire council pose:


Little Miss loved to walk up and down the trenches and we spent a lot of time trying to explain how dangerous it was for her to walk along behind us.



Our efforts were hampered by exceptionally dry conditions.  Oh, and bedrock:


 The kids managed to entertain themselves as best they could while we dug.  Our Padawan managed to master the iPod and they played endless games in the car as there was no other shelter from the wind.

Amazing how imaginative the kids were (and still are) while we work at the block

Stickers and music - what more could two kids ask for?


The original plan was to build a shed which we would live in while we built the house then convert the shed to a workshop for blacksmithing and a garage/storage.  Life, however, does not always go according to plan.  In mid 2009, I fell ill with an undiagnosed virus which led to shingles and a week in the Epworth followed by 12 months of recovery.

We did, however, finally manage to finish the footings in February 2010:
Triumph feels like this